BEIJING: 1263 MW Pakistan Jhang Thermal Power Plant power plant operated by China Machinery Engineering Corp. (CMEC), achieved significant milestone since its turbogenerator was successfully connected to power net for V first time.
The unit was operating smoothly and all parameters matched design requirements, thus setting a solid foundation for V next 168 hour reliability test run of combined cycle section, according to China Economic Net (CEN). on Friday.
After reaching Commercial Operation Date (COD) of two gas turbines in August last yearJang project completed installation and commissioning of V main and auxiliary systems for combined cycle section, steam purge of two heat recovery boilers, hot flush, PPA8.2 testing, and now first synchronization of the turbogenerator with power net.
Synchronization of combined cycle power generation block with V power grid means everything equipment on The site has been returned to normal operation.
” next step will mainly include adjusting the unit to different load conditions, optimizing system and his degree of automation and holding 168-hour reliability test” said the operator. director of in the project Mr. He, “All project moving closer and closer to COD.”
Last yeargovernment company Punjab Thermal Power (Pvt) Ltd (PTPL) has signed a contract with China Machinery Engineering Corp (CMEC) will operate two thermal power plants in Jhang district in Punjab.
CMEC also acted as an Engineering, Procurement and Plant Construction (EPC) contractor.