KARACHI: Online with a Supreme Court (SC) order, the 15-story Nasla Tower was razed to the ground down completely.
According to the administration, the demolition continued for 24 hours and five heavy machinery were used to demolish the building.
The process has begun on November 28, 2021 and it took 69 days to take down the building. However, the lifting of the debris is in processes.
Before on On October 25, 2021, the SC had ordered the Karachi authorities to demolish the Nasla Tower through a controlled implosion within a week.
In its detailed verdict, the apex court referred officials to use the latest technology demolish the high-rise building on the Shahrah-e-Faisal via a controlled explosion.